On site now

Ongoing projects

Work currently under execution, documented stage by stage with site photography from subgrade and sub-base works through to structural and mechanical installation.

Live works

Progress on the ground

Cold storage facility under construction in Sindh
In progressSindh, Pakistan

Atmosphere Control Stores

Wahab Engineering Services (Pvt.) Ltd. provides end-to-end solutions for cold storage facilities, including planning, civil and structural construction, insulated panels installation, flooring, refrigeration coordination, electrical and HVAC support, and complete project management. We ensure energy-efficient, durable, and standards-compliant cold storage buildings tailored to food, agriculture, and pharmaceutical storage needs.

  1. Civil and structural works

    Foundations, structural frame and flooring built to carry insulated panel systems and heavy refrigeration loads.

  2. Insulation and refrigeration coordination

    Insulated panel installation coordinated with refrigeration, electrical and HVAC trades to protect the cold chain.

Prepared road subgrade in the mountains of Gilgit
In progressGilgit and Astore, Gilgit-Baltistan

Astor Valley Road

A strategic highway package linking Astore with the neighbouring Neelam Valley, improving freight mobility and regional integration. The works run from subgrade preparation through sub-base compaction to reinforced concrete culvert construction, all executed to approved drawings, technical specifications and safety standards, with allowance for seismic requirements and the harsh mountain climate.

  1. Subgrade preparation

    Excavation, filling, leveling and compaction to achieve the specified bearing capacity and density across mountain terrain.

  2. Sub-base placement and testing

    Placement, grading and compaction of the sub-base layer, with density and level checks recorded before the next course.

  3. RCC culvert slabs

    Supply, cutting, bending and fixing of reinforcement steel for culvert slabs, detailed for seismic requirements.

Progress on site

Prepared road subgrade in the mountains of Gilgit
Stage 1: subgrade excavated, leveled and compacted
Compacted sub base layer of a new highway in Gilgit
Stage 2: sub-base placed and checked for density
Reinforcement steel fixed for an RCC culvert slab in Gilgit
Stage 3: reinforcement fixed for RCC culvert slabs
See completed projects